What type of relationship is being shown between activities C and E?

Prepare for the Certified Associate Constructor (CAC) Level 1 Exam with our quiz. Study with engaging questions and comprehensive explanations. Perfect your test knowledge today!

In project management, understanding the type of relationship between activities is crucial for scheduling and resource allocation. The finish-to-start relationship indicates that the preceding activity, in this case, activity C, must be completed before the subsequent activity, activity E, can begin. This is the most common type of relationship used in project scheduling.

Recognizing that activity E cannot commence until activity C is finished demonstrates a logical flow of tasks. This kind of relationship helps ensure that the dependencies are respected, leading to a more organized and efficient progression of the project timeline.

Other relationships, such as start-to-start or finish-to-finish, suggest different dependencies that do not apply in this scenario. A start-to-start relationship would mean that both activities could commence at the same time, which would not fit the context if E relies on the completion of C. A finish-to-finish relationship indicates that both activities must be completed together, which also does not align with the presented scenario if E cannot start until C is finished. Lastly, a start-to-finish relationship, which is less common, indicates that the start of one must precede the finish of another, further reinforcing that the conditions of the question suggest a finish-to-start relationship.

Thus, stating that the relationship between activities