What is the late start for activity H in project planning?

Prepare for the Certified Associate Constructor (CAC) Level 1 Exam with our quiz. Study with engaging questions and comprehensive explanations. Perfect your test knowledge today!

In project planning, the late start of an activity refers to the latest time that an activity can begin without delaying the overall project schedule. To determine the late start for activity H, one needs to consider various factors, including the duration of the activity, its dependencies, and the project's overall timeline.

To arrive at this answer, it's important to analyze the project network diagram, find the critical path, and understand the earliest start and completion times of preceding activities. If activity H has a duration that aligns with the overall scheduled finish and allows for any dependencies without causing delays to subsequent activities, then a late start of 5 would indicate that activity H can be completed without impacting the project timeline.

Finding the late start involves backward pass calculations from the project’s end date, deducting the durations of the dependent activities to find the latest possible start while still adhering to the project completion date. Therefore, if the calculations substantiate that starting activity H at 5 is the most delayed yet feasible approach without affecting the project's end date, this would validate the answer.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy